TM-9-2350-260-20-1-2 M60 Hull Organizational Maintenance Volume 2 Download

Page 52 of 772

TM 9-2350-260-20-1-2 POWERPLANT REPLACEMENT (2D ENGINE) (Sheet 17 of 28) 9. Install six spring washers (A) (three on each side) to top of transmission mounts. 10. Using hoist with sling, lift powerplant into position over engine compartment. 11. Use personnel to guide powerplant into hull. 12. Make sure transmission rollers (B) fit into both powerplant guides (C). 13. Lower powerplant into installed position. When powerplant is seated, remove both fabricated final drive guide shields. 14. Check that powerplant is correctly seated. Check all clearances around powerplant 15. Remove four sling hooks from four lifting eyes of powerplant. Go on to Sheet 18 TA147943 5-42