Figure 5-122 Figure 5-121 Figure 5-123 Figure 5-124 Install twenty-four self-locking nuts (A). Tighten nuts evenly to 19 to 23 pound-feet torque. Install right and left power takeoff covers and gaskets (A). Secure each cover with six bolts and six plain washers. Tighten bolts to 15 to 20 pound-feet torque. Reposition transmission, bottom side up. Install output flange (A), bolt (B), locktab (C), and seal ring (D). Using torque wrench (A), tighten bolt to 83 to 100 pound-feet torque while holding flange (B) with tool (C). Remove tool (C). 5-54