13. Install clamp (Figure 6, Item 14) on cable bundle and secure with clamps (Figure 6, Item 14) and (Figure 6, Item 16) to hull with screw (Figure 6, Item 15). 14. Install four clamps (Figure 6, Item 14) on cable bundle. Secure with four screws (Figure 6, Item 13). 15. Install new tie straps (Figure 6, Item 12) as required. Figure 6. RF Cable/Signal Patch Panel Box – Connect. END OF TASK FOLLOW ON MAINTENANCE 1. Connect battery ground lead, see (TM 9-2350-277-13&P). 2. Set MASTER SWITCH to ON, see (TM 9-2350-277-13&P). Check that electrical system works properly. 3. Set MASTER SWITCH to OFF, see (TM 9-2350-277-13&P). END OF TASK END OF WORK PACKAGE TM 9-2350-277-40&P 0037.2 0037.2‐7/8 blank CHANGE 1