TM 9-2350-277-20-3 ADJUST SERVICE BRAKE CONTROL LINKAGE — Continued 0407 00 4. Loosen jam nut (6) on linkage rod (7). Install rod on cross-shaft link (1). 5. Adjust length of linkage rod (7) by turning rod end bearing (8) until clevis pin (9) inserts freely into bearing and cross-shaft link (1). Tighten jam nut (6). WARNING Failure of control linkage can cause carrier to crash. Crash could kill or injure personnel. Install NEW cotter pin. 6. Secure linkage rod end bearing (8) to cross-shaft link (1) with two washers (10), clevis pin (9), and new cotter pin (11). FOLLOW-THROUGH STEPS 1. Install hull front access cover (WP 0449 00). 2. Install driver’s power plant access panel (see your -10). 3. Close power plant front access door (see your -10). 4. Raise trim vane (see your -10). END OF TASK 0407 00-4