TM-9-2350-277-20-3 Unit Maintenance Manual Volume 3 M113A3 M577A3 M1064A3 M1068A3 M58 Download

Page 470 of 962

TM 9-2350-277-20-3 REPLACE TRANSMISSION WIRING HARNESS — Continued 0360 00 INSPECTION-ACCEPTANCE AND REJECTION CRITERIA INSPECTION AND REPAIR 1. Check leads for continuity. Replace bad leads. 2. Check connectors and terminals. Repair bad connectors or terminals (WP 0382 00). INSTALLATION 1. Place new wiring harness (1) on transmission. 2. Connect circuit 323 connector (2) to differential pressure switch (3). 3. Connect wiring harness connector (4) to transmission connector (5). 4. Connect circuit 366 lead (6) to transmission low oil pressure switch (7). 5. Connect transmission wiring harness connector (8) to bulkhead connector (9). 6. Install wiring harness (1) in four clamps (10), and secure to brackets with four screws (11), eight washers (12), and four new locknuts (13). FOLLOW-THROUGH STEPS 1. Close power plant access door (see your -10). 2. Raise trim vane (see your -10). END OF TASK 0360 00-2