TM 9-2350-261-34 INSTALL PERSONNEL HEATER KIT (M113A2 AND M1059 ONLY) — Continued 0055 00 9. Install grommet (6) in power plant bulkhead. 10. Install exhaust pipe (7) in grommet (6). 11. Install exhaust pipe (8) on exhaust pipe (7). 12. Secure two exhaust pipes (8) and (9) and two gaskets (10) to power plant bulkhead with four screws (11) and retained nuts (12). 13. Install gasket (13) on exhaust elbow (14) and insert elbow through top deck into exhaust pipe (9). 14. Install gasket (15) on intake elbow (16) and position elbow through top deck opening. 15. Secure exhaust and intake elbows (14) and (16) to top deck with six screws (17). 16. Secure exhaust pipe (9) to elbow (14) with U-bolt (18), clamp (19), and two nuts (20). 0055 00-4