TM-9-2350-261-20-3 Unit Maintenance Manual Volume 3 M113A2 M577A2 M1064 M1068 M1059 M901A1 Download

Page 48 of 936

TM 9-2350-261-20-3 REPLACE POWER PLANT DOOR — Continued 0427 00 3. Install bracket (4) on left end of power plant door (6), with door in open position. Secure brackets (3) and (4) to hull with four washers (2), and screws (1). Do not tighten screws. NOTE Do Step 4 if power plant door does not clear top of opening. 4. Place plates (5) under brackets (3) and (4). After each plate is installed, tighten screws (1) until power plant door (6) clears top of opening. 5. TIGHTEN FOUR SCREWS (1) TO 216-240 LB-IN (24-27 N·M) TORQUE. Use torque wrench. 6. Remove lifting device and sling from power plant door. FOLLOW-THROUGH STEPS 1. Close and lock power plant door (see your -10). 2. Connect and raise trim vane (see your -10). END OF TASK 0427 00-4