TM-9-2350-261-20-3 Unit Maintenance Manual Volume 3 M113A2 M577A2 M1064 M1068 M1059 M901A1 Download
Page 47 of 936
REPLACE POWER PLANT DOOR — Continued INSTALLATION 1. Install two spacers (7) on ends of power plant door (6). WARNING Damaged slings can fail when loaded. Breaking slings can strike and injure personnel. Suspended load can fall and crush personnel. Inspect all slings before use. Do not use damaged slings. Clearly mark all damaged slings as DAMAGED - DO NOT USE. WARNING Hanging loads, heavy parts, and overhead equipment can fall unexpectedly and kill or injure you. Stay clear of hanging loads, heavy parts, and overhead equipment. Use correct lifting devices. Always have helper guide heavy parts and equipment. 2. Connect suitable lifting device around power plant door (6) and position on hull. Have helper assist. 0427 00-3 0427 00 TM 9-2350-261-20-3