TM 9-2350-247-20-1 REMOVE/INSTALL POWER PLANT (M548A1) — Continued 0130 00 INSPECTION-ACCEPTANCE AND REJECTION CRITERIA C A U T I O N Steam clean power plant only. Do not use cleaner or solvent which could damage rubber and plastic. 1. It tactical situation permits, steam clean power plant compartment. Make sure it is ready to receive power plant. INSTALLATION WARNING Make sure lifting device has rated lift capacity of at least 2500 lb (1135 kg) to safely raise the power plant. Keep all parts of body from under the suspended load. 1. (H) Attach beam type sling (1) to lifting device. Slowly raise power plant and lower it into power plant compartment. Keep slight tension on sling. 0130 00-14