TB-9-2350-368-25 Powerplant Test Stand M113A2 M113A3 M548A1 M548A3 Download
Page 92 of 120
TB 9-2350-368-25 4-20 WARNING • Damaged lifting slings can fail with load. Personnel can be killed or injured. Inspect all slings before use. Do not use damaged slings. • Hanging loads can kill or injure you. Keep away from hanging loads and overhead equipment. Keep hands out of area while powerplant is being lifted for removal or lowered for installation. 51. Attach powerplant sling to lifting brackets and lift powerplant assembly from powerplant test stand. Have helper assist. 52. Remove screw, nut, and washer from right gransfer gearcase hole. 53. Remove transfer gearcase mount, screw, nut, and two washers from the left transfer gearcase hole. 54. Prepare powerplant for work or storage area. Refer to TM 38-260. Ensure that powerplant is stable before removing sling. END OF TASK