TM-9-2520-234-35 Technical Manual for M109 Transmission XTG-411-2A Download
Page 221 of 323
PAR 228, STEPS 15-18 ASSEMBLY CHAP 5, SEC XXXIII Figure 342 (Step 15) Install lockup clutch plate (A). Install lockup clutch back plate (B). Aline bolt holes. Figure 343 (Step 16) Install torque converter turbine assembly (A), meshing the splines of the turbine hub with those of lockup clutch plate (B). Figure 344 (Step 17) Install stator assembly (A). Install torque converter pump assembly (B). Install two 5/16-24 nuts, 180° apart, to hold converter assembly together. Turn assembly over on assembly table. Figure 345 (Step 18) Install the remaining twenty-two 5/16-24 nuts (A). Using a 1/2-inch wrench, torque all of the nuts, alternately and evenly, to 19-23 pound-feet. 189