TM-9-2350-358-BD M109A6 Battlefield Damage Assessment and Repair Download

Page 252 of 343

TM 9-2350-358-BD 11-15. BYPASSING FAILED COMPONENTS - CONTINUED 1. Disconnect the tee in the hydraulic supply line from the reservoir to the manual elevation and equilibration hand pumps from the bulkhead fitting at the reservoir. 2. Using a 1/4-inch cap, cap the bulkhead in step 1. 3. Install a 1/4-inch straight adapter into the tee disconnected in step 1. 4. Connect a 7/16-inch hose onto the straight adapter in step 3. 5. Submerge the hose from step 4 into a utility pail. Fill with clean hydraulic fluid. 6. Record the BDAR action taken. When mission is complete, as soon as practical, repair the equipment/system using standard maintenance procedures. 11-34