ARMY TM 9-1290-365-24&P Date: __________________ Tested by: __________________ Inspected by: __________________ D.4.13 Troubleshooting. This paragraph contains the troubleshooting procedures for UUT failures detected during testing. It is arranged in the sequence of test steps, and provides information on addi- tional test steps required for the malfunction isolation. Refer to Figure FO-1 for the interconnection dia- gram of the UUT. WARNING Do not point the radiating surface towards any personnel. Do not bring eyes to close contact with the radiating surface. Use absorbing materials in front of the radiating surface whenever possible. CAUTION This equipment contains assemblies subject to damage by electrostatic discharge. Use approved grounding procedures before touching, removing or inserting printed wiring assemblies. D-45