TB-9-2320-280-35-15 HMMWV Technical Bulletin Installation for Retransmission EPLRS Network Manager Download
Page 100 of 168
5-76 TB 9-2320-280-35-15 33-19. Locate, mark, and drill one 0.147-in. hole (42) in top of windshield frame (2). 33-20. Route DAGR antenna cable (6) on top of windshield frame (2) and secure with loop clamp (34) and self-tapping screw (33). 33-21. Route DAGR antenna cable (6) down through center access hole (37) of integrated rack (38), and coil excess antenna cable (6) under integrated rack (38). 33-22. Route DAGR power cable (40) from bracket (39) to right-side tunnel insulation (41). NOTE Loosen right-side tunnel insulation before performing step 33-23. (Refer to TM 9-2320-280-20.) 33-23. Route DAGR power cable (40) under edge of right-side tunnel insulation (41) to 24V terminal bar at cab enclosure panel. Figure 5-90. 33. SELF-TAPPING SCREW – 9421073 – QTY. 1 34. LOOP CLAMP – MS21333-65 – QTY. 1 38. DAGR POWER CABLE – 9728558-10 – QTY. 1 33 42 34 6 2 38 39 40 41 37 ~ ~