MOS-94P Multiple Launch Rocket System (MLRS) Repairer M142 HIMARS Download

Page 70 of 188

Performance Measures GO NO-GO 2. Removed the W75 or W76 cable assembly. _____ _____ 3. Removed the defective intermediate beam. _____ _____ 4. Installed the replacement intermediate beam. _____ _____ 5. Installed the W75 or W76 cable assembly. _____ _____ 6. Verified that the intermediate beam was operational. _____ _____ 7. Completed maintenance forms, if required. _____ _____ Evaluation Guidance: Score the soldier GO if all performance measures are passed (P). Score the soldier NO-GO if any performance measure is failed (F). If the soldier fails any performance measure, show what was done wrong and how to do it correctly. References Required DA Form 2404 DA Pamphlet 750-8 EM 0208 TM 9-1055-647-13&P TM 9-243 3-40 1 October 2014