TM-9-2320-366-34-3 MTV Direct Maintenance Manual M1083 Series - Volume 3 Download
Page 463 of 1178
TM 9-2320-366-34-3 NOTE Left and right side hydraulic hoses are installed the same way. Left side shown. (11) Install two fittings (14) and nuts (15) on mast (1). (12) Install hoses (16 and 17) on fittings (14). (13) Install four clamps (18) and eight screws (19) on mast (1). (14) Perform steps (11) through (13) on right side hoses (16 and 17). c. Follow-On Maintenance. (1) Install lift cylinders (para 16-37). (2) Install boom assembly (para 16-33). (3) Place hydraulic reservoir supply and return valves in open position (TM 9-2320-366-10-2). (4) Perform crane load test (para 16-62). End of Task. 16-227