TM 9-2320-366-20-5 Change 2 20-491 20-78. DIGITIZATION KIT REMOVAL This task covers: a. Removal b. Follow-On Maintenance INITIAL SETUP Equipment Conditions Engine shut down (TM 9-2320-366-10-1) Batteries discounted (para 7-57) Kick panel removed (para 16-3) Power distribution panel removed (para 7-11 WTEC II, Para 7-13 WTEC III) RH seat removed (para 16-15) Tools and Special Tools Tool Kit, Genl Mech (Item 46, Appendix C) Materials/Parts Lockwasher (2) (Item 113.1 Appendix G) Lockwasher (6) (Item 107.1 Appendix G) Nut Self-Locking (6) (Item 146.1 Appendix G) Personnel Required (2) a. Removal. (1) Remove nut (1), lockwasher (2), washer (3), and terminal lug TL21 (4) from ground stud (5). Discard lockwasher. (2) Install washer (3) ground stud (5) with nut (1). NOTE Retain digitization kit parts for future use. NOTE Other terminal lugs are present at this location.