TM-9-2320-365-10 LMTV Operator Manual M1078 Series Download

Page 297 of 836

TM 9-2320-365-10 WARNING WARNING Ensure there are at least two wraps of cable on hoist drum at all times. Cable could come off hoist drum while load is being lifted. Failure to comply may result in injury to personnel or damage to equipment. CAUTION • If circuit breaker trips while Light Material Handling Crane (LMHC) is operating, allow 30 minutes to cool down. If load is suspended, reset circuit breaker and lower load. If circuit breaker trips again, notify Unit Maintenance. Failure to comply may result in damage to equipment. • Do not jerk hoist control switch causing load to bounce. Failure to comply may result in damage to equipment. (4) Place hoist control switch (2) in down position to reel in cable (3) and lift load. (5) Swing boom (1) to place load in desired location (para 2-24h). (6) Place hoist control switch (2) in up position to lower load. (7) Remove hook (4) from load. 2-197