Mccarthy Hitt - Next Nga West Joint
Venture
CAGE Code: 7SVK7
NCAGE Code: 7SVK7
Status: Active
Type: Commercial Supplier
Summary
Mccarthy Hitt - Next Nga West Joint, Venture is an Active Commercial Supplier with the Cage Code 7SVK7.
Address
12851 Manchester Rd
Saint Louis MO 63131-1802
United States
Points of Contact
No Points of Contact...
Related Information
No Related Information...
People who viewed this 'CAGE Code' also viewed...
Abdelmalek & Associates Inc. Pace Dh Dba Overhead Door Co Anheuser-Busch, Llc Imaging Resources Inc Alban Scientific, Inc. Loose Leaf Metals Co Mci Telecommunications Corp Koven Technology, Inc Robert N Covington Webb Kenneth W And Associates Environmental Management And N & J Railroad Contractors Inc. American Gateway Moving And Storage Braznell Co Noble Oak Creative Llc Brainz & Hustle Llc Mettler-Toledo Inc Gold Star Mobile Services & Six Sigma Unique Expression
Frequently Asked Questions (FAQ) for CAGE 7SVK7
- What is CAGE Code 7SVK7?
- 7SVK7 is the unique identifier used by NATO Organizations to reference the physical entity known as Mccarthy Hitt - Next Nga West Joint Venture located at 12851 Manchester Rd, Saint Louis MO 63131-1802, United States.
- Who is CAGE Code 7SVK7?
- 7SVK7 refers to Mccarthy Hitt - Next Nga West Joint Venture located at 12851 Manchester Rd, Saint Louis MO 63131-1802, United States.
- Where is CAGE Code 7SVK7 Located?
- CAGE Code 7SVK7 is located in Saint Louis, MO, USA.
Contracting History for CAGE 7SVK7 Most Recent 25 Records
- W912DQ19C7001
- Modification For Spg Stair Enclosures Incurred Costs, Library Changes, Powder-Coated Underfloor Basket Tray To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 10 Dec 2021
- Modification For Spg Stair Enclosures Incurred Costs, Library Changes, Powder-Coated Underfloor Basket Tray To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $741,595,744.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Divide Mail Room Space, Create Csoc Suite, And S64 Changes To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 5 Apr 2022
- Modification Of Divide Mail Room Space, Create Csoc Suite, And S64 Changes To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $743,217,457.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification To Acs For Pdr Cabinets And Utv Storage Relocation To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 12 Jan 2023
- Modification To Acs For Pdr Cabinets And Utv Storage Relocation To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $747,674,630.00
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Remove A9 Spaces From Mcn Suite, Special Function Dining Room Doors, S37 Lab Changes, And S19 Space Changes To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 15 Oct 2021
- Modification For Remove A9 Spaces From Mcn Suite, Special Function Dining Room Doors, S37 Lab Changes, And S19 Space Changes To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $738,686,726.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Architectural Room Numbering To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 27 Jul 2021
- Modification For Architectural Room Numbering To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $702,251,779.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Rf Shielding Isolated Spaces, Aba Support Space - Spg West, And Ameren Substation Design Change To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 2 Mar 2022
- Modification For Rf Shielding Isolated Spaces, Aba Support Space - Spg West, And Ameren Substation Design Change To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $742,933,282.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Sbsa Utility Extensions, Descope Bench Pad To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 22 Sep 2023
- Modification Of Sbsa Utility Extensions, Descope Bench Pad To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $749,960,570.00
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Additional Survey Markers For Rif Water Line Upsize, Photocatalytic Incurred Costs, S61 Voip And Lab Telecom Relocate Door, Booster Pump Bypass, Delete Select Door Closers To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 4 Aug 2021
- Modification For Additional Survey Markers For Rif Water Line Upsize, Photocatalytic Incurred Costs, S61 Voip And Lab Telecom Relocate Door, Booster Pump Bypass, Delete Select Door Closers To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $702,251,779.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Weather Time Extension Jan 21 - Mar 21 Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 18 May 2021
- Modification For Weather Time Extension Jan 21 - Mar 21 Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $672,157,544.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Add Break Area To Lower Level To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 24 May 2021
- Modification For Add Break Area To Lower Level To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $672,157,544.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Aba Support Space - Spg East, Retail Space Security Grilles, Wsc Suite Additions To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 23 Nov 2021
- Modification For Aba Support Space - Spg East, Retail Space Security Grilles, Wsc Suite Additions To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $739,357,165.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Ne Security Fence Realignment, Increase Workstations In Suite S62, Fitness Center Floor Outlets, Spg Camera Requirements 120V, Das Requirements To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 13 Jul 2021
- Modification For Ne Security Fence Realignment, Increase Workstations In Suite S62, Fitness Center Floor Outlets, Spg Camera Requirements 120V, Das Requirements To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $701,753,864.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Interlock At Area F Transitions, Omit Painting Tier 3 Exposed Ceilings To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 2 Jun 2022
- Modification Of Interlock At Area F Transitions, Omit Painting Tier 3 Exposed Ceilings To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $746,359,880.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Rea - Ifms Level 4 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 5 Jul 2023
- Modification Of Rea - Ifms Level 4 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $749,960,570.00
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Weather Time Extension Oct 21 - Dec 21 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 24 Jan 2022
- Modification Of Weather Time Extension Oct 21 - Dec 21 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $741,908,933.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Wsu Suite Changes, Mcp Training Room, And Relocate Commercial Connections In Fdr To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 10 Mar 2022
- Modification For Wsu Suite Changes, Mcp Training Room, And Relocate Commercial Connections In Fdr To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $742,841,690.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Rea Ifms Level 5 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 4 Aug 2022
- Modification For Rea Ifms Level 5 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $746,783,295.00
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Wao Enclave Colors In Public Hub, Fcc Ahu Relocation To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 8 Sep 2022
- Modification Of Wao Enclave Colors In Public Hub, Fcc Ahu Relocation To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $746,783,295.00
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Weather Time Extension Jan 22 - Mar 22 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 19 Apr 2022
- Modification Of Weather Time Extension Jan 22 - Mar 22 To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $743,217,457.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Addt'l Sec Trans Between H2u And H3c Protected Cable Pathways Increase Pdr Size To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 7 May 2021
- Modification For Addt'l Sec Trans Between H2u And H3c Protected Cable Pathways Increase Pdr Size To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $672,157,544.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Network Clocks & Room Reservation System, Hybrid Fiber For Wireless, Rtls Cabling, Ids Infrastructure, Signal Cabling For Ipms, Acs Infrastructure, Cctv Infrastructure In Mob And Cup To Contract For Project Eero Design-Build Contract At St. Louis, Mo. 0151 Special Systems Time Impact
- 3 Sep 2021
- Modification For Network Clocks & Room Reservation System, Hybrid Fiber For Wireless, Rtls Cabling, Ids Infrastructure, Signal Cabling For Ipms, Acs Infrastructure, Cctv Infrastructure In Mob And Cup To Contract For Project Eero Design-Build Contract At St. Louis, Mo. 0151 Special Systems Time Impact
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $703,020,512.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Admin - High Bay 35/65 Clin Split To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 17 Aug 2021
- Modification For Admin - High Bay 35/65 Clin Split To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $702,583,936.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Change Control Team To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 2 Sep 2021
- Modification For Change Control Team To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $703,020,512.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification For Vcc Ballistic Protection & Waste Disposers In Break Areas/Kitchen To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 3 Jun 2021
- Modification For Vcc Ballistic Protection & Waste Disposers In Break Areas/Kitchen To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $673,664,127.40
- Department Of Defense (Dod)
- W912DQ19C7001
- Modification Of Admin Mod - Phase 1, Inc Adjustments To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- 13 Sep 2022
- Modification Of Admin Mod - Phase 1, Inc Adjustments To Contract For Project Eero Design-Build Contract At St. Louis, Mo.
- W071 Endist Kansas City
- Department Of Defense (Dod)
- $746,783,295.00
- Department Of Defense (Dod)