Roy Anderson Corp
CAGE Code: 0C6F6
NCAGE Code: 0C6F6
Status: Active
Type: Commercial Supplier
Dun & Bradstreet (DUNS): 007850530
Summary
Roy Anderson Corp is an Active Commercial Supplier with the Cage Code 0C6F6 and is tracked by Dun & Bradstreet under DUNS Number 007850530..
Address
11400 Reichold Rd
Gulfport MS 39503-6008
United States
Points of Contact
Related Information
People who viewed this 'CAGE Code' also viewed...
Land Shaper Inc Willowshade Art Studio Beepers Unlimited 3 Girls Painting Youth Of Tomorrow Summer Enrichment Cooper Thelma Decorating Center The Deas Tire Co Auto Rentals Inc Dba Hertz System Gulf Coast Lawn Care Mississippi Filing Systems Inc Macton Construction Inc Broadwater Beach Resort Harrison County Wastewater Sernac Galleries Inc Mccaffrey Stanley Signs Cutrer Pamela S Ph D Terminix Services Br 0005 Southcoast Lawn Care Services Radio Shack
Frequently Asked Questions (FAQ) for CAGE 0C6F6
- What is CAGE Code 0C6F6?
- 0C6F6 is the unique identifier used by NATO Organizations to reference the physical entity known as Roy Anderson Corp located at 11400 Reichold Rd, Gulfport MS 39503-6008, United States.
- Who is CAGE Code 0C6F6?
- 0C6F6 refers to Roy Anderson Corp located at 11400 Reichold Rd, Gulfport MS 39503-6008, United States.
- Where is CAGE Code 0C6F6 Located?
- CAGE Code 0C6F6 is located in Gulfport, MS, USA.
Contracting History for CAGE 0C6F6 Most Recent 25 Records
- 1605AE21C0012
- Under Change Order No. 001 Requires All Labor, Material And Equipment Required To Remove An Additional 1,000 Cubic Yards Of Dirt/Debris At Building F.
- 26 May 2022
- Under Change Order No. 001 Requires All Labor, Material And Equipment Required To Remove An Additional 1,000 Cubic Yards Of Dirt/Debris At Building F.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $46,914,844.58
- Department Of Labor (Dol)
- 1605AE21C0012
- This Item Provides Reimbursement Of Rac To Provide All Labor, Material And Equipment Required To Remove All Unsuitable Soil Interfering With The Installation Of Foundation F23a To Be Replaced With Flowable Fill.
- 3 Mar 2023
- This Item Provides Reimbursement Of Rac To Provide All Labor, Material And Equipment Required To Remove All Unsuitable Soil Interfering With The Installation Of Foundation F23a To Be Replaced With Flowable Fill.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,250,479.05
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides For All Labor, Materials And Equipment Required To Make Pile And Grade Beam Changes At Building F Due To The Unforeseen Force Sewer Main.
- 1 Sep 2022
- This Modification Provides For All Labor, Materials And Equipment Required To Make Pile And Grade Beam Changes At Building F Due To The Unforeseen Force Sewer Main.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,103,676.13
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides For The Additional Excavation To Uncover And Repair An Existing Force Sewer Main At Building F And Provides A Credit To The Government For Work No Longer Required.
- 25 Aug 2022
- This Modification Provides For The Additional Excavation To Uncover And Repair An Existing Force Sewer Main At Building F And Provides A Credit To The Government For Work No Longer Required.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,096,334.42
- Department Of Labor (Dol)
- 1605AE21C0012
- This Revisions Provides All Labor, Material And Equipment Required For The In-Field Framing Adjustment As Described Under Asi No.13 For Building A At The Gulfport Job Corps Center.
- 20 Jul 2023
- This Revisions Provides All Labor, Material And Equipment Required For The In-Field Framing Adjustment As Described Under Asi No.13 For Building A At The Gulfport Job Corps Center.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,606,165.06
- Department Of Labor (Dol)
- 1605AE21C0012
- This Revisionn Provides For All Labor, Material And Equipment Required To Allow For The Implementation Of The Services Outlined In The June 3, 2023, Notice To Proceed, With The Grout Work At Building A.
- 14 Jun 2023
- This Revisionn Provides For All Labor, Material And Equipment Required To Allow For The Implementation Of The Services Outlined In The June 3, 2023, Notice To Proceed, With The Grout Work At Building A.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,562,499.32
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides All Labor, Material And Equipment For The Revisions To The Existing Walls At Building A, As Outlined In The Government's Response To Rfi 404, 401 And 398.
- 7 Sep 2023
- This Modification Provides All Labor, Material And Equipment For The Revisions To The Existing Walls At Building A, As Outlined In The Government's Response To Rfi 404, 401 And 398.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,639,438.18
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Requires All Labor, Material And Equipment Required For The Relocation Of An Existing Water Main At Building F.
- 4 May 2022
- This Modification Requires All Labor, Material And Equipment Required For The Relocation Of An Existing Water Main At Building F.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $46,597,036.50
- Department Of Labor (Dol)
- 1605AE21C0012
- The Purpose Of This Modification Is To Incorporate Eo 14026 Into The Requirements.
- 21 Apr 2022
- The Purpose Of This Modification Is To Incorporate Eo 14026 Into The Requirements.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $46,567,143.87
- Department Of Labor (Dol)
- 1605AE21C0012
- Rac Shall Provide All Labor, Materials And Equipment Required To Provide The Temporary Offices Required In Accordance With Section Section 1.3.D., Of The Contract Specification.
- 22 Sep 2022
- Rac Shall Provide All Labor, Materials And Equipment Required To Provide The Temporary Offices Required In Accordance With Section Section 1.3.D., Of The Contract Specification.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,210,685.04
- Department Of Labor (Dol)
- 1605AE21C0012
- This Revisions Provides All Labor, Material And Equipment Required For Changes To The Grading And The Elimination Of Chain Walls At The East Side Of Building F For The Redevelopment Of The Gulfport Job Corps Center.
- 15 Aug 2023
- This Revisions Provides All Labor, Material And Equipment Required For Changes To The Grading And The Elimination Of Chain Walls At The East Side Of Building F For The Redevelopment Of The Gulfport Job Corps Center.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,613,361.69
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides Complete Settlement Of All Costs Incurred By Roy Anderson Corporation (Rac) Due To The Structural Steels Issues Encountered At Building A During The Development Of The Gulfport Job Corps Center.
- 19 Sep 2023
- This Modification Provides Complete Settlement Of All Costs Incurred By Roy Anderson Corporation (Rac) Due To The Structural Steels Issues Encountered At Building A During The Development Of The Gulfport Job Corps Center.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $48,299,438.18
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides A Credit To The Government As A Result Of The Revisions In Construction Which Deletes The Requirement For Manhole 5 At Building A.
- 8 Nov 2023
- This Modification Provides A Credit To The Government As A Result Of The Revisions In Construction Which Deletes The Requirement For Manhole 5 At Building A.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $48,297,665.32
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Settles Rac's Additional Costs For Management, Supervision, Administration And Escalation Costs Associated Due To Protest, Ce#001.
- 14 Apr 2022
- This Modification Settles Rac's Additional Costs For Management, Supervision, Administration And Escalation Costs Associated Due To Protest, Ce#001.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $46,567,143.87
- Department Of Labor (Dol)
- 1605AE21C0012
- This Revisions In Construction Provides All Labor, Material And Equipment Required For The Addition And Installation Of A 3"Pipe With Hub Drain In Response To Pco 032, Titled Cooling Tower Drain, For The Redevelopment Of The Gulfport Job Corps C
- 6 Jul 2023
- This Revisions In Construction Provides All Labor, Material And Equipment Required For The Addition And Installation Of A 3"Pipe With Hub Drain In Response To Pco 032, Titled Cooling Tower Drain, For The Redevelopment Of The Gulfport Job Corps C
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,604,722.48
- Department Of Labor (Dol)
- 1605AE21C0012
- Construction Of Approximately 90,000 Gross Square Feet Of Six New Buildings Including Administration/Education, Dining, Vocation Shops, Recreation, Facilities Maintenance, And A Chiller Plant On An Area Of Five Acres At The Gulfport Job Corps Center.
- 25 Jun 2021
- Construction Of Approximately 90,000 Gross Square Feet Of Six New Buildings Including Administration/Education, Dining, Vocation Shops, Recreation, Facilities Maintenance, And A Chiller Plant On An Area Of Five Acres At The Gulfport Job Corps Center.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $42,989,000.00
- Department Of Labor (Dol)
- 1605AE21C0012
- Modification No. P00005 Is Deleted In Its Entirety, Which Results In A Credit To The Government For All Labor, Materials And Equipment As Outlined In The Executed Modification.
- 26 Sep 2022
- Modification No. P00005 Is Deleted In Its Entirety, Which Results In A Credit To The Government For All Labor, Materials And Equipment As Outlined In The Executed Modification.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,175,427.72
- Department Of Labor (Dol)
- 1605AE21C0012
- This Revision In Construction Provides All Labor, Material And Equipment To Allow For The Implementation Of The Services Outlined In Request For Proposal 002 Dated May 12, 2023 And Its Associated Scope Of Work Dated May 11, 2023 To Include 3/4"
- 6 Jun 2023
- This Revision In Construction Provides All Labor, Material And Equipment To Allow For The Implementation Of The Services Outlined In Request For Proposal 002 Dated May 12, 2023 And Its Associated Scope Of Work Dated May 11, 2023 To Include 3/4"
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,517,675.08
- Department Of Labor (Dol)
- 1605AE21C0012
- This Item Provides For All Labor, Material And Equipment Required To Remove The Existing Masonry, Clean And Paint The Existing Steel, And Install The New C-Channels As Outlined In The Scope Of Work Dated March 7, 2023.
- 27 Mar 2023
- This Item Provides For All Labor, Material And Equipment Required To Remove The Existing Masonry, Clean And Paint The Existing Steel, And Install The New C-Channels As Outlined In The Scope Of Work Dated March 7, 2023.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,314,741.66
- Department Of Labor (Dol)
- 1605AE21C0012
- The Contract Period Of Performance Is Extended By 4 Calendar Days Due To Unusually Sever Weather Conditions.
- 20 Apr 2023
- The Contract Period Of Performance Is Extended By 4 Calendar Days Due To Unusually Sever Weather Conditions.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,508,480.75
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Provides For All Labor, Materials And Equipment Required For The Changes In The Hardware Schedule, And For The Deletion Of Piers At Building A.
- 19 Sep 2022
- This Modification Provides For All Labor, Materials And Equipment Required For The Changes In The Hardware Schedule, And For The Deletion Of Piers At Building A.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,108,677.76
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Resolves The Rac's May 4, 2002, Request For Additional Cost Associated With The Implementation Of E.O. 14024, And Downtown Associated With Exploratory Borings For The Center Redevelopment Project At The Gulfport Job Corps Cente
- 16 Jun 2022
- This Modification Resolves The Rac's May 4, 2002, Request For Additional Cost Associated With The Implementation Of E.O. 14024, And Downtown Associated With Exploratory Borings For The Center Redevelopment Project At The Gulfport Job Corps Cente
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,001,981.33
- Department Of Labor (Dol)
- 1605AE21C0012
- This Item Provides Reimbursement Of All Costs Associated With The Implementation Of Minimum Wage Increase Effective January 1, 2023.
- 8 Feb 2023
- This Item Provides Reimbursement Of All Costs Associated With The Implementation Of Minimum Wage Increase Effective January 1, 2023.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $47,218,742.01
- Department Of Labor (Dol)
- 1605AE21C0012
- This Modification Requires All Labor, Material And Equipment Required To Rework The South Bank Of Brickyard Bayou.
- 11 May 2022
- This Modification Requires All Labor, Material And Equipment Required To Rework The South Bank Of Brickyard Bayou.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $46,632,293.82
- Department Of Labor (Dol)
- 1605AE21C0012
- The Contractor Shall Provide All Labor, Material And Equipment Required To Remove And Dispose Of The Additional Layer Of Asbestos-Containing Material For Transite Sub-Roofing Located At The Existing Cafeteria.
- 23 Mar 2022
- The Contractor Shall Provide All Labor, Material And Equipment Required To Remove And Dispose Of The Additional Layer Of Asbestos-Containing Material For Transite Sub-Roofing Located At The Existing Cafeteria.
- Dol - Jcas - Aec
- Department Of Labor (Dol)
- $43,067,143.87
- Department Of Labor (Dol)